Customer :

SUMMIT LNG

Role :

Main Contractor

Key date :

2018-2019

Location :

Maheshkhali Island - Bangladesh, Asia

Description of the Project

EPCI of the second LNG floating storage and regasification terminal (FSRU)

Work done and added value of our solution

Offshore Terminal & Gas Pipeline Installation

  • Number of Pipelines                  1 x Import Gas Line

  • Length of Line                                6,500m / 40m water depth

  • Diameter                                           24’’

  • Plug specifications                      Plug Mooring System

  • Number of anchors                     8 Suction Piles & 3 Holdback Anchors

  • Mooring Lines                                Mixed PE & Chains